Policy Statement
As System Operator, Transpower has a contract with the Electricity Commission to co-ordinate and manage the real time transmission of electricity – 24 hours a day, seven days a week.
The System Operator's obligations are set out in Part C of the Electricity Governance Rulebook. These obligations include a Policy Statement (Part C Schedule C4) on how Transpower will meet those obligations.
The System Operator reviews the Policy Statement annually, as required by the Electricity Governance Regulations and Rules.
Timeline
| Activity | Date | Duration |
| Participants to provide initial ideas for review |
Mid Feb |
|
| System Operator workshop with those participants providing input - to consider System Operator review proposals |
Early Mar |
|
| System Operator completes draft and undertakes informal discussions with participants |
Mar |
|
| Draft Policy Statement submitted to Board |
31 Mar |
|
| Draft Policy Statement published |
30 Mar |
within 20 business days |
| Submission period |
|
not less than 10 business days |
| SO Submission period |
|
10 business days after closing of submission period |
| Board to make recommendations to Minister |
|
|
| Policy Statement Active |
01 Sep |
12 months |
2010 Draft Policy Statement
The draft Policy Statement for 2010 has now been submitted to the Electricity Commission and is available on their website for viewing. The Electricity Commission will be starting their consultatation process in the near future.